Water Project Update for the week ending: 5/3/2019

Cliff street 100'of 10" water main was installed this week along with  valves for a hydrant and valves for Marion Ave.Weather has been a damper on getting up to full speed. Much of the piping and supplies has been delivered and things should pick up from here. At the tank site the road has been installed and the prep for  
the foundation continues.