Water Project Update for the week ending: 5/3/2019
Cliff street 100'of 10" water main was installed this week along with valves for a hydrant and valves for Marion Ave.Weather has been a damper on getting up to full speed. Much of the piping and supplies has been delivered and things should pick up from here. At the tank site the road has been installed and the prep for the foundation continues.