Update on the Water Project for week ending 5/17/19

Cliff St. 450ft. of 10" PVC pipe and appurtenances (an accessory).  Bloom St. 555 ft of HDPE pipe (drilled ) installed.  

Water Tank Site prepped and ready to start forming up the foundation next week.