Mayor's Blog
Sunday, June 16, 2019
Water Update for Week ending 6/14/2019
Water Update for Week Ending 6/14/2019
Finishing up Rip RAP ( Loose Rock used on any waterways or water containment where there is potential for water erosion) on Cliff St. Drilling crew drilled and installed 400ft on Spring St.
No comments:
Post a Comment
Newer Post
Older Post
Home
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment