Week of 6/24 - 6/28
Water Tank Construction Continuing.
The drill crew is finishing up drilling on Spring St. @ Vine St. Drilling the last 400ft . So for the month the drill crew installed 537 ft of 10" HDPE Pipe
and 1437 ft. Of 8" HDPE Pipe.
The open cut crew was following behind connecting all the pipes,valves and fire hydrants at the intersections of Commercial St., Elm St., Bloom and Maple St..
We are planning to finally start on Marion St (Rt. 51) on Monday.
We will be using traffic lights on Rt. 51 for traffic control. Please use caution around area of maple St., Cliff St. And Commercial St.. Thanks again for being patient with us during all this work.
We will not be working Thursday and Friday due to Holliday.
We hope you all have safe and great Fourth of July!!