Tuesday, October 22, 2019

Water Project Exceeded Time for Completion

Water Project Update:  The contractor has exceeded the time for completion of contract number 1,  (Water Mains).  We are working with the contractor to prioritized restoration and pavement. 

We are also working with them to install meters, once we receive updated schedules from the company.  Contractors will be back in spring to complete the project. 




Sunday, October 20, 2019

Water Project Update 10/20/19

The month of September crews were working on tying in new water mains at intersections of Spring St. And Vine St. (2), Sylvan St. And Rt. 51, Bloom St. And Green St., Green St. And Vale St., Rt.51 and Vale St. (2), Rt.51 @ bridge (West), Rt.51 @ bridge (East), Grove St. And Bloom St., Bloom St. @ wetland, Spring St. and Maple St., Spring St. And Sylvan St..
Also crews were hooking up services to new water main ( Spring St., Bloom St., Rt. 51and Commercial St.).
The black top crew is busy working on street restoration.
We apologize for the traffic delays and rough roads. thank you for your patience during construction. We're working hard to complete this project and get things back to normal in your Village.
Thank you!!!!!

Monday, October 14, 2019

Delay in Meter Installation

As most of you are aware meter installation has not started.  The contractor is waiting on more parts to come before they can begin.  I will let you know as soon as I know when this will begin.  Thank you all for your continued patience with this project.


Saturday, October 12, 2019

Planned Closure of Spring Street October 14th For Water Project

Our Water Project Contractor is planning on closing Spring Street on Monday, October 14, 2019 to open cut water services.  Columbus Day holiday. Detour is provided below!  If you didn't get a Call From the Village, Please contact the Village Office During Regular Hours to get your phone number added to the list.  There will be possible water outages during this time.



Please be aware that the appropriate Police, Fire and EMS entities will be contacted in advance, when the closure is in place, and when it is removed.

George Sisley, Resident Representative for the Water Project

George Sisley, is our Resident Project Representative that works for the Engineering Firm of Dodson and Associates.  He oversees all activities with our water project and represents our interests.  He should be involved with the meter installation.  No meters have yet been installed, I'm currently looking into the delay.  Thank you for your continued patience.

Saturday, October 5, 2019

Meter Installers Pictures and Names


SUBCONTRACTORS:
A.TREFFEISEN & SONS LLC
204 ROUNDHOUSE ROAD
ONEONTA, NY 13820
607-432-1655

 INSTALLERS PICTURES





Larry Stepp
Lee March

Michael Heller

Michael Perry
Christopher Clark
Nathan Sheldon

Eric Stafford
David Reardon