Report for week of 9/2 - 9/6
Crews working on essential tie ins on water mains to switch over old tank to new tank. The switch was made Wednesday. Crews are still working on tie ins and also installing new services for houses. The blacktop crew is still doing blacktop restoration. We are scheduled to have crews on Rt. 51 to install new services for houses.
Hi Mark, What is happening with Sylvan Street? No one has done anything along our street just the top, at 51 and at the crossroads at Spring.
ReplyDelete