Water Update for Week of 9/9-9/15

 Water Update for Week of 9/9-9/15
Crews are continuing with service hook ups to new water main on Rt 51 and Bloom st. 
Also crew is doing water main tie ins at Green st and Vale and Rt 51.
Black top crew is continuing with black top on Spring, Bloom, and Rt 51. 

Sunday, September 8, 2019

Report for week of 9/2 - 9/6


Report for week of 9/2 - 9/6


Crews working on essential tie ins on water mains to switch over old tank to new tank. The switch was made Wednesday. Crews are still working on tie ins and also installing new services for houses. The blacktop crew is still doing blacktop restoration. We are scheduled to have crews on Rt. 51 to install new services for houses.
We will continue to have water shut offs on some houses as they install new services.  We will do our best to let you know. 

Sunday, September 1, 2019

Water Shut Off Tuesday

Tuesday will be a big tie in for water mains!! The water will be shut off for an hour or so between 8:00 and noon! The new mains will be hooked to the old on Spring&Vine and Sylvan & Marion. The new water tank will then be put into service.

Report for week of 8/26 - 8/30

Report for week of 8/26 -8/30


Excavating services on old mains to remove lead water lines. All lead service lines must be removed.  Installed a new fire hydrant on Rt 51 @house #3 and Rt 51 @ #39.

Also two water main tie ins to get ready to put new water tank online, one on Rt 51@ maple and one on Hilton and Bloom. Also blacktop being placed .